Chesire
Road and 3Bs and K Road
Delaware County, OH
A feasibility study for improving the intersection
of Chesire Road and 3 B’s and K Road. The study included providing
short-term recommendations with estimated costs and evaluating
three conceptual alternatives for project feasibility and
preparing preliminary cost estimates. The three conceptual
alternatives studied were signalized intersection including
appropriate turn lanes on existing alignment, signalized intersection
including appropriate turn lanes on improved alignment, and
a modern roundabout. Korda performed the following in preparation
of the final report: gathered sight distance and other necessary
field data, developed future traffic volumes based on coordination
with MORPC regional model, analyzed traffic volumes and developed
narrative and tables summarizing existing and future conditions,
and developed short-term and long-term recommendations with
estimated costs.
|